EAST CHINA · Typhoon measures and onward connections
East China port waits eased before
typhoon measures prompted schedule changes
On October 20, Shanghai's seven-day average vessel wait fell to 2.14 days from 2.61 days. Navigation restrictions announced afterward in response to Typhoon Champi mean that this earlier figure cannot establish normal operating conditions after the weekend.
Shanghai average wait2.14 days2.61 days on Oct 13 → 2.14 days on Oct 20Before the typhoon impact · Seven-day average
Vessels at anchor off Shanghai and Ningbo98 vesselsWaiting capacity of approximately 585,000 TEUOct 21 count
Reported delays on some mainline services3–4 daysBased on relevant carrier and sailing noticesNot a confirmed delay for every sailing
The October 23 notices included restrictions on Yangtze estuary entry, northbound departures and inland-vessel operations, with different vessel categories and effective times. They should not be interpreted as a simultaneous halt to all operations at every Shanghai and Ningbo terminal.
The supplied materials contain notices and forecasts through October 23, so the lifting of restrictions and actual resumption of work after the weekend require separate confirmation. For Korea–China and Southeast Asian cargo routed through East China, assess how mainline delays affect onward feeder connections.
Weekly Check PointBefore gate-in, confirm terminal acceptance, whether navigation restrictions have been lifted, and the vessel's updated berthing and departure times. If a transshipment connection changes, use confirmed capacity on the alternative sailing and the revised final arrival date to adjust trucking and warehouse appointments.
PHILIPPINES · Waiting times and empty returns
Manila waits grow longer,
and other ports are not automatic alternatives
3.72 days Manila seven-day average vessel wait
Oct 20 · Previously 2.59 days on Oct 13
Manila continues to face vessel waits and limited capacity for storing and returning empty containers. Some carriers' restrictions on new bookings reportedly also cover Subic and Batangas. Changing the destination port alone therefore does not ensure acceptance.
Vessel waiting time also differs from the time needed to collect a container after customs clearance. Delays in terminal appointments and empty-container returns can affect subsequent truck trips.
Weekly Check PointFor new shipments, first confirm acceptance by carrier and destination port. For arriving cargo, align collection appointments with the designated empty-return location, then coordinate the next pickup and the receiving factory or warehouse's available hours.
BUSAN & TRANSSHIPMENT · Terminal differences
Busan's lower average vessel wait
does not establish terminal gate-in availability
On October 20, Busan's seven-day average vessel wait edged down to 1.0 day from 1.07 days. BNCT yard occupancy was nevertheless reported above 90%, so the port-wide average improvement does not imply that every terminal has more gate-in capacity.
Changes to arrival order or connecting vessel schedules after Chinese navigation restrictions may also affect cargo departing from or transshipping through Busan. Coordinate the arriving and connecting vessels as one schedule rather than checking each in isolation.
Weekly Check PointDispatch trucks in line with the assigned terminal's gate-in window and vessel cutoff. For transshipment cargo, check the time between actual discharge completion and the connecting vessel's cutoff. Share revised arrival dates with production and receiving teams when connections change.